The new acute care tower at Prince Albert Victoria Hospital reached the halfway point this June, and the province says it's on schedule to be finished by spring 2028. If you live in South Hill, you've watched it grow. What you see from 24th Street West is the part Saskatchewan is paying for. The beds, monitors, imaging machines and surgical tools that make it a working hospital come from a separate $40 million community campaign, and that campaign is still going.

So with about a year and a half to go, the structure is the predictable part of this project. The open question is the inside, and that's the part neighbors can actually affect.

What half-built looks like right now

The province's update on June 1, 2026 is the most recent official progress report. PCL Construction Ltd. had finished assembling the main structure, rooftop heliport included. Exterior insulation was nearly done, cladding was going on, and crews were working through mechanical and electrical systems along with interior finishes like drywall and door frames.

PCL Project Director Grant Selinger said the project had passed one million worker hours.

The timeline has also gotten tighter. When the province signed PCL in February 2024, paNOW reported completion would come sometime in 2028. The June 2026 release narrows that to spring 2028. That's a more precise target, not a later one.

What's going inside, measured against what's there now

The tower's main job is capacity. The province puts the increase at about 40 per cent. Here's how the headline numbers compare with today's hospital:

Today When the tower opens
Inpatient beds 174 242
Bassinets in the Malhotra Neonatal Intensive Care Unit 11 13, in the new tower
MRI None in the region The region's first

The plan also includes larger emergency and operating rooms, dedicated pediatrics and maternity units, a new adult mental health unit, an expanded intensive care unit and the rooftop heliport. Prince Albert Grand Council Grand Chief Brian Hardlotte said the council had input from the early stages, including on a dedicated First Nations and Métis cultural space.

Look at that list again, though. Every item depends on equipment. A bigger emergency department needs gear inside it. An MRI suite is just a room until the machine shows up.

The line between the province's budget and the community's

Saskatchewan is funding the construction. The Boreal Healthcare Foundation says its Equip the Vic campaign has to cover the furnishings, fixtures, equipment and technology the tower needs to open and run. The province's own release thanks the foundation, the City of Prince Albert and surrounding communities for contributing to the cost of furniture, fixtures and equipment.

The campaign's goal is $40 million. Of that, $35 million goes to equipment, technology and patient-care tools, and $5 million goes to a long-term healthcare endowment.

Foundation CEO Cody Barnett put it plainly in the June release:

"It is only a building until the community raises the funds to equip it with the technology and tools it needs to serve patients, and that is exactly what the Equip the Vic Campaign is here to do. With completion on the horizon, the commitments being made today will determine what kind of hospital opens in 2028."

The province has a firm target date for the building. The equipment depends on the campaign, which has no comparable public finish line.

Where the money has come from so far

The foundation hasn't published a running total for Equip the Vic. What is public is a set of named gifts and event results.

paNOW's June 2026 progress story listed earlier major gifts:

  • Cameco, $1.5 million
  • SIGA, $375,000
  • Redhead Equipment, $150,000
  • The Hudye family, $150,000
  • Aaron and Sherry Palidwar, $100,000

Local events have added to that this year. The 2026 Med Gala, presented by MNP, raised $142,376 from tickets, sponsorships and auctions, and the proceeds went to Equip the Vic. In June, the Lynx Northern Healthcare Classic raised $80,452. Brandt Tractor AG was the presenting sponsor, with support from Ruszkowski Enterprises, Lakeland Family of Dealerships and Lake Country Co-op.

Smaller events count too. On Saturday, August 8, a Baby Goat Yoga fundraiser at 4 Arabelle Road, east of the city, charged $35 a class. Proceeds went to Equip the Vic.

If you add up every gift and event total named in that coverage, you get roughly $2.5 million. That's only the publicly reported amounts, not the campaign's real total, since many donations are never announced. Still, it gives you a sense of scale. The big corporate gifts make up most of that figure, and the $40 million target is far larger. Reaching it will take a lot of smaller contributions from across the region.

Getting to the Vic while the crane is still up

Until the tower opens, the hospital runs around an active construction site. Here's the latest guidance posted by the Saskatchewan Health Authority:

  1. Park on the south side. A May 13, 2024 notice closed the north public entrance and north parking lot for construction. It sent patients and visitors to the south visitor lot and the south-facing main entrance, and it added parking on that side, including more accessible stalls.
  2. Emergency access hasn't changed. The same notice said the emergency department, all south-side entrances and Herb Bassett Home stayed accessible as before. Pineview Terrace, Brief and Social Detox and the Family Treatment Centre are reached through the south entrance into the campus.
  3. Give yourself extra time. If you used to come in through the north entrance for appointments, the SHA recommended allowing an extra 20 to 30 minutes, depending on your mobility.
  4. Pay before you leave. The SHA's current Victoria Hospital page lists pay parking at two on-site locations. If you exit through the main entrance, you pay for parking there. It describes the North (Therapies) Entrance as pay-and-display.

That facility page isn't dated, and it doesn't say whether it replaces the 2024 directions. Treat both as the latest posted guidance and follow the signs on the grounds, as the SHA asks. The province says PCL and the SHA are working to keep disruption low for visitors and staff, and that it doesn't expect any impact on patient care.

The next date on the calendar

The next big public fundraiser is Give a Little Life Day, the radiothon, which is marking 20 years. It runs on December 4 at the Lake Country Co-op Food Store and broadcasts live on all of Prince Albert's Pattison Media stations.

This year's donations support the foundation's full mission, including Equip the Vic. Gord and Barb Broda are matching every gift. You can also donate before December 4 through the Give a Little Life Day site or the Equip the Vic campaign page.

The building is on schedule for spring 2028. What it opens with is still being decided, and the December radiothon is the next chance to add to it.

If you own a home in South Hill and want to understand how a major build like the Vic fits into your own plans, whether you're staying put, renovating or thinking about a move, I'm happy to talk it through with you. I'll be straight about what we know so far and what we don't. Brooke Wozniak is here when you're ready. Book a consultation.